Posted on: July 10, 2020

August 14, 2020 Bevins/Bichner/Talahi Project Update

2020 Bevins/Bichner/Talahi Utility Extension Project Update Sign (IMAGE)

Project Information 

Construction on the Bevins, Bichner, and Talahi Utility Extension Project continued this week with the installation of services on Bichner Lane, the continued installations on Warner Avenue, and dewatering preparations for the...

Read on...

Home Page
Posted on: May 7, 2020

August 14, 2020 12th Newsletter 2020 Birchwood Rd/Lost Lake Project

2020 Birchwood/Lost Lake Ct Project Update Sign (IMAGE)

Project Information 

This week, the City’s contractor began placing the roadway sub-base and aggregate. The roadbed work will continue into the beginning of next week, followed by the installation of concrete curb and gutter. Currently, ...

Read on...

Home Page
Posted on: May 8, 2020

August 13, 2020 Phase 4 West Historic District Project Update

2020 Phase 4 West Construction Update (IMAGE)

The contractor has scheduled curb to be installed along Quail Street, Park Avenue (from Quail to Rose), and Rose Street for Wednesday, August 19th. The timing and curb locations are subject to change. If curb installation requires you to move your vehicle...

Read on...

Home Page
Posted on: August 10, 2020

Renter Relief Grant Program

Renter Relief Program Wash Co (IMAGE)

Help is available for qualified Washington County residents who are unable to pay rent and utility costs due to COVID-19 related income loss.Washington County received $31.7 million from the CARES Act, and the County Board determined that $3 million will ...

Read on...

Home Page
Posted on: July 29, 2020

Homeowners and Small Business Financial Relief

Homeowners Small Business Financial Relief Covid Vertical (IMAGE)

Financial Relief available for Washington County homeowners

Homeowners in Washington County who have experienced a reduction in income because of the COVID-19 pandemic may apply for one-time grants of up to $10,000 to help make housing payments.

A separate ...

Read on...

Home Page
Posted on: May 21, 2020

May 21, 2020 Dahlia Street Project 2nd Newsletter

2020 Dahlia Street Project Update Sign (IMAGE)

The City’s contractor, T.A. Schifsky & Sons, is currently finishing on the installation of watermain and water services within Dahlia Street. Following this, crews will finish the remaining tree removals (as marked by a red ‘X&...

Read on...

Home Page
Posted on: May 20, 2020

Get an Absentee Ballot

Absentee Ballot (IMAGE)

Statewide primary absentee voting begins on June 26th, and general absentee voting begins on September 18th. You can request an absentee ballot to vote early by visiting https://mnvotes.sos.state.mn.us/AB…/ABRegistrationStep1.aspx

Read on...

Home Page
Posted on: May 11, 2020

Detour Map - 2020 Phase 4 West Historic District

2020 Phase 4 West Historic District Detour Map (IMAGE)

THESE DETOURS ARE REQUIRED AS PART OF THE  PHASE 4 WEST - HISTORIC DISTRICT IMPROVEMENTS TO ALLOW FOR THE REPLACEMENT OF WATERMAIN VALVES.

DATES OF DETOURS ARE SUBJECT TO CHANGE. PLEASE DRIVE SLOWLY ON THE DETOUR ROUTE  AND AROUND CONSTRU...

Read on...

Home Page
Posted on: May 1, 2020

Phase 4 West Historic District Project

2020 Phase 4 West Construction Update (IMAGE)

The City of Mahtomedi’s consultant, WSB, is preparing for the start of construction on the Phase 4 West – Historic District Improvements. As announced at the neighborhood meeting in February, the project team is looking to use email an...

Read on...

Home Page
Posted on: September 13, 2019

2020 Dahlia Street Improvements Feasibility Report

2020 Dahlia Feasibility Report FINAL Front Cover (IMAGE)

The following is a feasibility report addressing street improvements for the 2020 Dahlia Street Improvement Project for the City of Mahtomedi. The roadway investigated in this report is: Dahlia Street between Mahtomedi Avenue and Warner Avenue. The propos...

Read on...

Home Page
Posted on: November 22, 2016

Website Personalization Now Available!

Street Car Park sign white flowers on front

By clicking “Log In” on the MyAccount bar at the top of the screen, users may create a login for the site or use their Facebook profile to access MyAccount. Once logged in, visitors can choose the modules, features and keywords that they’d like to see mos...

Read on...

Home Page