Project Information
This week, the City’s contractor began placing the roadway sub-base and aggregate. The roadbed work will continue into the beginning of next week, followed by the installation of concrete curb and gutter. Currently, the contractor is scheduled to pave the first layer of bituminous the week of August 27th. Please note this schedule is weather dependent, subject to change, and will be updated as necessary.
Information about the scope of improvements, frequently asked questions and project contacts are included in this newsletter. As the project progresses, should you have any questions, please reach out to the contacts listed below. During construction, an on-site representative will be present on site each day who will be your first point of contact and fastest way to get an answer for all questions regarding construction. Newsletters will be delivered or emailed weekly as the project progresses to inform property owners of the progress and upcoming construction schedule.
Construction working hours within the City of Mahtomedi are 7 am-7 pm during weekdays and 8 am-5 pm on Saturdays. Work is not permitted on Sundays or holidays.
2020 Birchwood Rd/Lost Lake Ct Project 12th Newsletter August 14, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 11th Newsletter August 10, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 10th Newsletter July 30, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 9th Newsletter June 30, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 8th Newsletter June 19, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 7th Newsletter June 12, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 6th Newsletter June 5, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 5th Newsletter May 29, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 4th Newsletter May 22, 2020 (PDF)
2020 Birchwood Rd Lost Lake Ct Project 3rd Newsletter May 15, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 2nd Newsletter May 7 2020 (PDF)
Dylan Casey - On-Site Representative
612-283-7466
Lydia Ener - Project Engineer
763-270-3464
lener@wsbeng.com
Nick Guilliams - Project Manager
651-286-8468
Bob Goebel - Public Works Director
651-773-9730