Project Information
Due to safety concerns during construction activity, the east entrance of Birchwood Road at Wildwood Beach Road is closed to all vehicle, bicycle, and pedestrian traffic until further notice. Please follow all detour and closure signs on the roadway.
This week, the City’s contractor installed the concrete fence bases, and aggregate shouldering. Next week, the fence will be installed along trail adjacent to the wetlands, and the wear course will be paved on Monday. During paving operations, vibratory rollers will be used for compacting the bituminous pavement. These may cause vibrations at your home, but the vibrations will be at safe levels. The roadway will not be closed during paving, but there may be temporary delays . We ask everyone to please drive carefully and following all signs and instructions from the contractor. Please note this schedule is weather dependent, subject to change, and will be updated as necessary.
Information about the scope of improvements, frequently asked questions and project contacts are included in this newsletter. As the project progresses, should you have any questions, please reach out to the contacts listed below. During construction, an on-site representative will be present on site each day who will be your first point of contact and fastest way to get an answer for all questions regarding construction. Newsletters will be delivered or emailed weekly as the project progresses to inform property owners of the progress and upcoming construction schedule.
Construction working hours within the City of Mahtomedi are 7 am-7 pm during weekdays and 8 am-5 pm on Saturdays. Work is not permitted on Sundays or holidays.
Dylan Casey - On-Site Representative
612-283-7466
Lydia Ener - Project Engineer
763-270-3464
lener@wsbeng.com
Nick Guilliams - Project Manager
651-286-8468
Bob Goebel - Public Works Director
651-773-9730
2020 Birchwood Rd/Lost Lake Ct Project 19th Newsletter October 2, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 18th Newsletter September 25, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 17th Newsletter September 18, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 16th Newsletter September 11, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 15th Newsletter September 4, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 14th Newsletter August 28, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 13th Newsletter August 21, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 12th Newsletter August 14, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 11th Newsletter August 10, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 10th Newsletter July 30, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 9th Newsletter June 30, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 8th Newsletter June 19, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 7th Newsletter June 12, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 6th Newsletter June 5, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 5th Newsletter May 29, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 4th Newsletter May 22, 2020 (PDF)
2020 Birchwood Rd Lost Lake Ct Project 3rd Newsletter May 15, 2020 (PDF)
2020 Birchwood Rd/Lost Lake Ct Project 2nd Newsletter May 7 2020 (PDF)