The City’s subcontractor, will be installing curb on Quail, Rose, Park Ave (Quail to Rose), and Tamarack Street on Wednesday August 19th and Thursday August 20th (weather dependent). If you live on these roadways you received a notice yesterday, Monday August 17th with more details. The District Education Center is available for residents to use as parking during this work. Please do not park on Quail, Rose, Park Ave (Quail to Rose), and Tamarack Street on these days so the contractor has adequate space to work.
Once the curb is placed it requires a five-day cure period. These streets will be too narrow to allow for parking during the curb curing time.
The road will appear to be narrower until the roadway is paved. Some of the driveways may not match in exactly with the new curb but this will be corrected prior to project completion.
This curb work, while temporarily inconvenient, will be a big step in completing construction. The contractor expects to pave these roadways within the next two-weeks, weather dependent.
As a reminder, the fastest way to get answers to questions on the project is to contact James Collingsworth at the number below via call or text. James will be on site each day. If you don’t hear back from James please then call, email, or text Alex Miller.
James Collingsworth - On-Site Representative
612-219-8082
Alex Miller - Project Engineer
612-518-5937
amiller@wsbeng.com
Nick Guilliams - Project Manager
651-286-8468
Bob Goebel - Public Works Director
651-773-9730
2020 Phase 4 West Historic District 3rd Newsletter July 2, 2020 (PDF)
2020 Phase 4 West Historic District 2nd Newsletter June 15, 2020 (PDF)
2020 Phase 4 West Historic District 1st Newsletter May 22, 2020 (PDF)
2020 Phase 4 West Historic District Property Owner Letter May 18, 2020 (PDF)
2020 Phase 4 West Historic District Project Property Owner Letter May 7, 2020 (PDF)