Posted on: June 1, 2022

July 1, 2022 Project Update - 2022 Street Improvement Project

2022 Street Projects Update (IMAGE)

2022 Street Improvement Project

July 1, 2022 Update -
Curb and gutter removal and replacement on Warner Avenue is now complete. The trail replacement along Warner Avenue will begin with removals on July 5th and continue with installation of new pavement. Pedestrian curb ramps on Warner Avenue will be installed the week of July 11th. There will be no construction on July 4th in observance of Independence Day. Construction on Locust Street and Maple Street is anticipated to begin week of July 11th. Please note that the schedule is tentative and subject to change weather depending.

Additional information about the project and project contacts can be found here: 2022 Street Improvement Project 1st Newsletter

Trail Detour Map: 2022 Street Improvement Project Trail Detours Map

Thank you for your patience as we work to improve the infrastructure in your neighborhood.

The quickest way to get answers to your questions on the project is to contact James Sharp at the number below. James will be on site each day. If you don’t hear back from James please contact Nick Guilliams. As construction progresses email updates will be sent weekly and hardcopy newsletters will be mailed bi-weekly. 
2022 Street Improvement Project Location Map (PDF)

James Sharp
On-Site Representative
612-655-5507

Nick Guilliams
Project Manager
651-286-8468

Bob Goebel
Public Works Director
651-773-9730

June 24, 2022 Update -
The curb and gutter on Warner Avenue will be completed today, June 24th. The trail replacement along Warner Avenue will begin with removals next week and continue with installation of new pavement the week of July 4th. There will be no construction on July 4th, continuing back up on July 5th.  Construction on Locust Street and Maple Street is anticipated to begin week of July 11th. Please note that the schedule is tentative and subject to change weather depending.

Additional information about the project and project contacts can be found here: 2022 Street Improvement Project 1st Newsletter

Trail Detour Map: 2022 Street Improvement Project Trail Detours Map

Thank you for your patience as we work to improve the infrastructure in your neighborhood.

The quickest way to get answers to your questions on the project is to contact James Sharp at the number below. James will be on site each day. If you don’t hear back from James please contact Nick Guilliams. As construction progresses email updates will be sent weekly and hardcopy newsletters will be mailed bi-weekly. 
2022 Street Improvement Project Location Map (PDF)

James Sharp
On-Site Representative
612-655-5507

Nick Guilliams
Project Manager
651-286-8468

Bob Goebel
Public Works Director
651-773-9730

June 10, 2022 Update -
Construction has started on the 2022 Street and Utility Improvement Project. A trail detour route is available for the Warner Avenue Trail and Streetcar Trail, which can be found at the link below. Locust Street between Warner Avenue and TH 244 will be closed for construction through mid-August. Next Tuesday, June 14th, Minnesota Paving and Materials will begin removing the trail, curb, end of driveways, and pedestrian ramps along Warner Avenue. Installation of the trail, curb, and pedestrian ramps will begin the week of June 27th. Construction on Maple Street and Locust Street will be starting after July 4th. Please note that the schedule is tentative and subject to change weather depending.  Thank you for your patience as we work to improve the infrastructure in your neighborhood.

The quickest way to get answers to your questions on the project is to contact James Sharp at the number below. James will be on site each day. If you don’t hear back from James please contact Nick Guilliams. As construction progresses email updates will be sent weekly and hardcopy newsletters will be mailed bi-weekly. 
2022 Street Improvement Project 1st Newsletter (PDF)
2022 Street Improvement Project Location Map (PDF)
2022 Street Improvement Project Trail Detours Map (PDF)

James Sharp
On-Site Representative
612-655-5507

Nick Guilliams
Project Manager
651-286-8468

Bob Goebel
Public Works Director
651-773-9730


May 31, 2022 Update - 
The 2022 Construction season is about to begin! The City’s contractor, Minnesota Paving and Materials is planning to begin work within the project area the week of June 6th, weather permitting. The contractor will begin with removal of the existing trail along Warner Avenue. Following this work, the contractor will remove and replace concrete curb & gutter and sidewalk along Warner Avenue. The remainder of the schedule includes complete road reconstruction of Maple Street from TH 244 (Mahtomedi Avenue) to Warner Avenue, complete road reconstruction of Locust Street from TH 244 (Mahtomedi Avenue) to Warner Avenue, and the milling and paving of Warner Avenue from CR 12 (Stillwater Road) to Maple Street. Please note that the schedule is subject to change. More detailed schedule information will be provided via email for those who have signed up for email updates.

The quickest way to get answers to your questions on the project is to contact James Sharp at the number below. James will be on site each day. If you don’t hear back from James please contact Nick Guilliams. As construction progresses email updates will be sent weekly and hardcopy newsletters will be mailed bi-weekly. 
2022 Street Improvement Project 1st Newsletter (PDF)
2022 Street Improvement Project Location Map (PDF)
2022 Street Improvement Project Trail Detours Map (PDF)

James Sharp
On-Site Representative
612-655-5507

Nick Guilliams
Project Manager
651-286-8468

Bob Goebel
Public Works Director
651-773-9730