The following is an updated feasibility report from the report submitted to the City Council on
August 6, 2018 addressing utility improvements for the Bevins, Bichner, & Talahi Utility Extension
for the City of Mahtomedi. The report was updated to reflect the findings of a cost benefit
appraisal report that was prepared for the lands affected by this proposed improvement. The
portions of the report that have been updated are shown in red text in this report. Roadways
investigated in this report include Bevins Lane, Bichner Lane, Talahi Drive, and Warner Avenue
South. The proposed improvements include sanitary sewer improvements along all the above referenced
roadways and watermain improvements along Bichner Lane, Bevins Lane, and
Warner Avenue South. This project was initiated by petition.
2019 Bevins, Bichner & Talahi Utility Extension Updated Feasibility Report (PDF)